Cherry Creek High School
Photo Gallery
Video Gallery
Fast Facts
Cherry Creek High School
 
2008 Bond Project Info
 
2008 Enrollment 3,713
 
Size / Square Feet 471,632
 
Year Opened 1953
 
Site Acreage 81
 
Architectural Firm n/a
 
General Contractor n/a
 
Projected Start Date June 2009
Project Completion Date
 
Project Details
Remodel Projects
n/a

Electrical / Mechanical Projects
1) East Building: upgrade lighting systems; replace heating water boiler; replace plumbing fixtures

2) West Building: upgrade lighting systems; replace campus-wide public address system; install fire suppression system; replace swimming pool circulation system; replace plumbing fixtures in science lab; replace boiler system piping; replace north gymnasium HVAC equipment

3) Fine Arts: replace lighting systems and public address system; replace emergency generator; upgrade theatre fire suppression system; minor plumbing upgrades

4) Information Center: upgrade lighting systems; replace emergency generator; replace telephone room air conditioner
 
Project Updates
Contractors Prepare to Bid on CCHS Bond Project
November 23, 2009
 
After school on Nov. 12, a group of about 30 general contractor and sub-contractors, armed with large rolls of architectural plans, toured the Cherry Creek High School West Building.  They peered into crannies above the ceiling tiles, trekked to the boiler room in the basement, and climbed through a small access window to examine the roof.   Their goal was to accurately assess the scope and challenges of a $1.8 million bond project, approved by Cherry Creek voters as part of the 2008... [More]